Chapter 7 : Utility
Services

1.
Introduction
2.
Electricity Supply
2.1 General
2.2 Electric Substations
2.3
Overhead Transmission Lines
2.4
Underground Cables
3.
Gas Supply
3.1
General
3.2
Piped
Gas Supply
3.3
Guidelines on Provision
4.
Telephone Service
4.1
General
4.2
Telephone Network
4.3
Telephone Exchanges
5.
Radio and Broadcast Communications
5.1
General
5.2
Guidelines on provision
6.
Water Supply
6.1
General
6.2
Locational Guidelines
7.
Drainage Services
7.1
General
7.2
Foul Sewerage System
7.3
Stormwater Drainage System
8.
Dedicated Utility Reserves
April 2002
Edition
1.1
The provision of utility services is fundamental to modern living. From a town planning
point of view, utility services are components of the basic infrastructure. The planning
of their provision should be integrated into the overall planning of new development areas
such that the efforts between various government departments and utility companies can be
co-ordinated.
1.2
This chapter provides planners with the basic information on electricity supply, gas
supply, telephone service, radio and broadcast communication, water supply and drainage
services. The guidelines would help planners in understanding the requirements of utility
services/facilities and enable them to work with various departments and utility companies
in the planning of new development areas.
2.1 General
2.1.1
Electricity supply is currently provided by the Hongkong Electric Company Limited (HEC)
(for Hong Kong Island and the neighbouring islands of Ap Lei Chau and Lamma) and the CLP
Power Hong Kong Limited (CLP Power) (for the whole of Kowloon, the New Territories and a
number of outlying islands including Lantau).
2.1.2
Electricity supply facilities include power generating stations, electric substations,
overhead lines and underground cables. Only the latter three items are discussed because
power generating stations are major territorial facilities requiring special
investigations on each project.
2.2 Electric Substations
2.2.1
Electricity is transmitted and distributed by different types of electric substations. The
CLP Power network includes extra high voltage (EHV) substations, bulk infeed
substations (BISs),
primary substations and consumer's substations. The HEC network includes bulk infeed
substations, primary substations and consumer's substations. The substations'
characteristics are discussed below:-
(a)
Extra High Voltage Substations & Bulk Infeed Substations (Switching Stations)
In the
CLP Power network, the EHV substations receive power from the power
stations or from other EHV substations at 400 kilovolt (kV) and supply the bulk infeed or
primary substations at 132kV. BISs receive power from EHV
substations or other BISs at 132kV and supply the primary substations at voltages ranging
from 33kV to 132kV and consumer substations at 11kV. In the HEC network, BIS receive power
from the power stations or from other BISs at 275kV or 132kV and supply the primary
substations at voltage of 66kV to 275kV.
(b)
Primary Substations (Zone Substations)
For the CLP Power
network, primary substations receive electric power at voltage of 33kV up to 132kV and
supply all the 11kV loads in the supply area. For the HEC network, primary substations
receive electric power at voltage of 66kV to 275kV and supply all the 22kV and
11kV loads in the
supply area.
(c) Consumer's
Substations (Distribution Substations)
Consumer's substations for CLP Power network receive power at a voltage of 11kV and deliver it at 380V.
Consumer's substations for HEC network receive power at a voltage of 22kV or 11kV and deliver it at 380V. There are two types of
consumer's substations:
(i)
Indoor Type (Transformer Room)
This is normally
provided with the consumers' premises.
(ii)
Outdoor Type
This is mainly found
in rural development areas and may be located either inside or outside the consumers'
premises.
2.2.2
Sufficient number of primary substations and BISs are required to meet
all the 22kV and 11kV loads in a supply area. In order to meet the demand for electricity supply in
a new town or re-developed area on time, it is recommended that the relevant utility
company be advised of the scale of development at an early planning stage. CLP Power or
HEC will investigate if demand can be met by the existing primary substations and
BISs, or new ones are required. With respect to the access, parking and
loading/unloading arrangements, Transport Department should be consulted at an early
planning stage. Please refer to Table 11 of Chapter 8 for parking and loading/unloading requirements.
Guidelines on
Provision
2.2.3
Extra High Voltage Substations & Bulk Infeed Substations
(Switching
Stations)
(a) These stations should be
located near to the pylons of transmission lines or major transmission cable routes (for
BIS) in the vicinity of the supply area and in an area which permits adequate cabling in
the access road(s) leading to the substations.
(b) They should be at least
200m away from the nearest fence of any telephone exchange, broadcasting or radio
communication installation. Additional advice should be obtained from the Director-General
of Telecommunications (DG, OFTA).
(c) As a major electric
substation will be a major source of noise nuisance, it should be located away from
residential or other sensitive uses wherever possible to minimize any noise problems. If
this is not feasible, suitable noise control measures will need to be included in the
design of the station (section 4.2.13 of
Chapter 9).
(d) The separation from
other buildings/structures should be at least 6m.
(e) Except with prior
approval of the Director of Fire Services (D of FS), no domestic units should be provided above
substations.
(f) The site requirement for
a typical EHV substation (with 6 x 240 MVA (Mega Volt-amp), 400kV transformers) is about
6500 m2 (100 m x 65 m). Free access via a carriageway of width not less than
6.5 m is required and the gradient should not exceed 1 in 12. These figures are for
reference only as each site reservation is subject to detailed examination. Additional
advice should be obtained from the Director of Electrical and Mechanical
Services (DEMS).
(g) The site requirement for
a typical BIS in the CLP Power network (with 4 x 50 MVA, 132/11kV
transformers) is about 2870 m2 (70 m x 41 m). In the HEC network, the site
requirement for a typical BIS, is between 1,504 m2 (32 m x
47 m for a station at 275kV level) and 2,550 m2 (30 m x 85 m for a station at
132kV level). Free access via a carriageway of not less than 4.5 m wide and with a
gradient not exceeding 1 in 10 is required. These figures are again for reference only and
individual site is subject to detailed assessment on a case by case basis. Additional
advice can be obtained from the DEMS.
2.2.4
Primary Substation (Zone Substations)
(a) They should be located
as near as possible to the supply area and should be adjacent to more than one road to
allow for adequate cabling requirement.
(b) They should be at least
200 m away from the nearest fence of any telephone exchange, broadcasting and radio
communication installation. Additional advice can be obtained from the DG, OFTA.
(c) Except with prior
approval of the D of FS, no domestic units should be provided above the
substation.
(d) The site requirement for
a typical primary substation in the CLP Power network (with 4 x 50 MVA, 132kV
transformers) is about 1705 m2 (55 m x 31 m). The site requirement for a
typical primary substation in the HEC network, with 4 x 60 MVA, 275 or 132kV transformers
is about 1600 m2 (40 m x 40 m). The depth of the building should be increased
by 11 m for each additional transformer to be installed. Free access via a carriageway of
not less than 4.5 m wide with a gradient not exceeding 1 in 10 is required. The figures
are again for reference only. Additional advice can be obtained from the DEMS.
2.2.5
Consumer's Substation (Distribution Substation)
(a) Indoor Type (Transformer
Room)
As this is normally provided within the
consumer's premises, the siting of the facility would be taken up with individual
developer with departments concerned.
(b) Outdoor Type
(i) It should be located as near as possible to
the area it serves.
(ii) Adjacent buildings or structures should have
a minimum fire resistant period of 2 hours failing which a physical separation of at least
3m should be allowed for.
(c) The typical substation
size for housing a 1.5 MVA, 22kV or 11kV transformer and associated control gear is 30.25 m2
(5.5 m x 5.5 m) for outdoor type and 51 m2 (8.5 m x 6 m) for indoor type.
(d) Access road with a width
of not less than 3 m is required.
2.3
Overhead Transmission Lines
Guidelines on
Provision
2.3.1
The location of new pylons and overhead transmission lines (OHL) should not be permitted
to dictate the pattern of future land use or to sterilize land which has a good
development potential. If the land is required for development, the existing transmission
lines, unless part of an approved scheme which is the subject of an order under the
Electricity Networks (Statutory Easements) Ordinance, may have to be relaid underground or
re-routed. However, the high cost involved in diversion should be given due consideration.
2.3.2
They should not be erected in existing developed areas, areas having substantial
development potential, and public open space, as far as practicable. Except in very
special circumstances, environmentally sensitive areas such as Sites of Special Scientific Interest (SSSI), conservation areas
and country parks should also be avoided.
2.3.3
Early consultation with the concerned departments at the planning stage is essential,
particularly on matters relating to locations of pylons and OHLs.
For extra high voltage transmission lines e.g. 400 kV, detailed site search reports with
full justifications should be prepared for consideration of relevant departments.
Environmental
Considerations
2.3.4
When the erection of permanent OHLs and pylons is planned, a
prudent approach should be adopted taking into account the following principles and
environmental considerations:
(a) They should be routed to
avoid as far as practicable, residential areas and environmentally sensitive areas such as
SSSI, conservation areas, country parks, ridgelines or locations which will seriously
affect the view from major residential developments.
(b) The location and design
of pylons should minimize the ecological and visual impacts on the landscape and nearby
residential developments.
(c) Damage to existing
vegetation through the erection of pylons should be minimized and landscape reinstatement
should be undertaken where necessary.
(d) Where permanent overhead
lines in environmentally sensitive areas covered by para. (a) cannot be avoided, the
Director of Agriculture and Fisheries (where development is within a country park), the
Director of Planning and Director of Environmental Protection should be consulted to
determine the appropriate type of planning and environmental assessment studies to be
undertaken and whether mitigation measures should be implemented to minimize any adverse
impacts identified. The Director of Home Affairs should also be consulted on the
appropriate level and means of public consultation which may need to be carried out.
(e)
For OHLs which are considered as Designated
Projects(1) under the Environmental Impact Assessment Ordinance (EIA Ordinance), the statutory EIA process must be followed and environmental permits are required for their construction and operation.
Footnote :
(1)
Designated Projects:According to Items H.1 and Q.1 of Schedule 2 of the EIA Ordinance,
transmission lines of 400kV in any location, or more than 66kV if they are within
environmentally sensitive areas, are considered as Designated Projects.
Safety
Considerations
2.3.5
For electrical safety considerations, provision should be made for
physical separation between conductors and adjacent buildings/structures. Depending on the
design of the structures supporting the conductors, the safety clearance should take the
magnitude of swing of conductors due to wind deflection into account. The respective
minimum safety clearances for various voltage levels of conducts (except 275kV
and 22kV which are conducted by underground cables) are given in Table 1.
Table 1 :Minimum Safety Clearance for Electrical
Safety Consideration
[Table Summary]
| Voltage Level (kV) |
Minimum Safety Clearance (m) |
400 |
5.5 |
132 |
3.7 |
66 |
3.2 |
33 |
2.9 |
11 |
2.9 |
2.3.6
Moreover, in the design of OHLs, adequate vertical ground clearance, which is measured
from the lowest point of the conductors (sagged point due to gravity) to the ground level,
should be provided. The determination of the minimum vertical ground clearance should take
the statutory requirements as laid down in the Electricity Supply Regulations into
account. The respective figures for various voltage levels are given in Table 2.
Table 2 :Minimum Vertical Ground Clearance for
Electrical Safety Consideration
[Table Summary]
| Voltage Level (kV) |
Minimum Vertical Ground Clearance (m)
|
400 |
7.6 |
132 |
6.7 |
66 |
6.1 |
33 |
6.1 |
11 |
6.1 |
2.3.7
The figures given in Tables 1 & 2 are for general reference purpose. To prevent
confusion and possible misinterpretation of the data, early consultation with the power
company and the Electrical and Mechanical Services Department (EMSD) will be necessary for
their application. Additional allowance for the safety clearance may be required by EMSD
to suit the actual site conditions.
2.3.8
In addition to the minimum safety clearance, allowance for the provision of a 6m emergency
vehicular access may be required, for fire fighting purposes, to reach the principal face
of any adjacent building development. Since each case will be considered on its merits,
consultation with the D of FS will be required regarding the detailed
arrangement.
2.3.9
To illustrate the above requirements, schematic drawings for 400kV and
132kV OHLs supported on pylon are given in Figure
1, Figure 2,
Figure 3 and
Figure 4 respectively.
Health Considerations
2.3.10
The electric and magnetic fields (EMF) emanating from OHLs are at extremely low frequency (50Hz) known as power frequency EMF. Although there is no
conclusive scientific evidence to date to support the hypothesis of adverse health effects
arising from exposure to power frequency EMF, the EMF exposure limit promulgated in the
guidelines issued by the International Commission on Non-ionizing Radiation Protection
(ICNIRP)(2) in 1998 are generally adopted as a prudent avoidance against the
influence of power frequency EMF. The development and research carried out on the subject
are closely monitored by departments concerned and the power companies.
2.3.11
In line with the guidelines issued by ICNIRP in 1998, the following standards on the
continuous public exposure limits for power frequency electric and magnetic fields are
recommended to the power companies by EMSD when the erection of permanent overhead
transmission lines is planned:
(a) The electric field strength(3) should not exceed
5kV per metre (r.m.s.); and
(b) The magnetic flux density(4) should not exceed
0.1 millitesla (r.m.s.) (i.e. 100 microteslas, r.m.s.).
The power companies should seek
further advice from EMSD at the design and planning stages of the overhead lines
concerned.
Footnotes :
(2) ICNIRP: The International Commission on Non-ionizing Radiation Protection (ICNIRP) was
established in 1992 as a successor to the International Non-ionizing Radiation Committee
of International Radiation Protection Association (IRPA/INIRC). The functions of the
Commission are to investigate the hazards that may be associated with the different forms
of the non-ionizing radiation, develop international guidelines on non-ionizing radiation
limits, and deal with all aspects of non-ionizing radiation protection.
(3) Electric Field Strength: This is the force exerted by an electric field on a medium.
Its magnitude is directly proportional to the voltage of the source and diminishes with
distance away from the voltage source. The electric field strength is expressed in terms
of volts per metre or kilovolts per metre.
(4) Magnetic Flux Density: This is the magnetic flux per unit area at a point in a
magnetic field. Magnetic flux is produced by electric current passing through a wire. Its
magnitude is directly proportional to the current and diminishes with distance away from
the current source. The unit of the magnetic flux density is microteslas or milliteslas.
2.3.12
In general, the physical separation provided by the preferred working corridor (para.
2.3.13 refers) has made allowance for the above consideration. However, at the early
planning stage of the OHLs, the power company concerned should provide the necessary
information to the EMSD for consideration.
Preferred
Working Corridor of Overhead Transmission Lines
2.3.13
For route protection and to provide sufficient space for pylon erection, operation,
inspection, maintenance, repair, renewal and removal of the equipment, a "preferred
working corridor" (as shown in Figure
1 and Figure 3) following the alignment of the OHLs, will be
required for general planning purpose. In the case of pole lines, in addition to the
"preferred working corridor", a "preferred working circle" is required
for pole erection as shown in Figure 5 and Figure
6.
2.3.14
The respective width of the preferred working corridor for 400kV and 132kV OHLs supported
on pylons are given in Table 3 and Figure
1 and Figure
3.
Table 3 :
Preferred Working Corridor for
400kV and 132kV OHLs supported on Pylons
[Table Summary]
Voltage
Level(kV) |
Width of the
Preferred Working Corridor (m) |
400 |
50 |
132 |
36 |
Note: Some of the 132kV OHLs are supported on pylons
2.3.15
For conductors supported on poles, e.g. voltage level from 132kV downwards, in addition to
the preferred working corridor, space is needed as a "preferred working circle"
to facilitate pole erection. The height of the pole has been taken into account in
determining the radius of the circle. In general, the alignment of OHLs and the location
of the supporting poles should avoid existing settlements as far as possible. The
respective figures of preferred working corridor and working circle for 132kV, 66kV, 33kV
and 11kV OHLs supported on poles are given in Table 4.
Table 4 :
Preferred Working Circle and
Working Corridor for Conductors Supported on Poles
[Table Summary]
Voltage
Level (kV) |
Width of the
preferred working circle to facilitate pole erection (m) |
Width of the preferred working
corridor (m)
|
132 |
36 |
21.4 |
66 |
24 |
13 |
33 |
24 |
12 |
11 |
24 |
10 |
2.3.16
Schematic drawings for 132kV OHLs supported on poles are given in Figure 5
and Figure 6.
2.3.17
Building developments will not be restricted in areas outside the preferred working
corridor and working circle subject to the provision of emergency vehicular access,
wherever appropriate, as required by Fire Services Department (FSD). For development within the preferred working
corridor and working circle, agreement from the EMSD, FSD and the power company should be
sought in order to ensure compliance of the safety and health considerations as given
above.
2.3.18
For example, N.T. village house development underneath 400kV OHLs
will be possible provided that the height of the conductors (sagged portion) is designed
not less than 15.6 m above the ground level. This clearance makes allowance for the
maximum height of the village house (8.23 m) and the average height of an antenna (1.87 m)
such that the minimum safety clearance of 5.5 m between antenna and the 400kV conductors
is maintained. However, agreement must be obtained from EMSD, FSD and the power company
before the commencement of any development or building works. An illustrative sketch is
given in Figure 7
.
2.3.19
Notwithstanding the above, the Land Authority should also notify the power company
concerned of any development (permanent or temporary) that is proposed within a distance
of 45m from overhead transmission lines.
Separation from
Telecommunication Lines on support
2.3.20
The alignment of the OHL should be separated from other telecommunication lines e.g.
telephone, on support. Reference should be made to the "Code of Practice - Protection
of Communication Networks From Electrical Power Distribution" issued by the
Director-General of Telecommunications (DG, OFTA) and OFTA.
2.4
Underground Cables
2.4.1
Cables are normally laid directly underground. Road openings to facilitate installation of
cables are subject to permission from the Highways Department. Projects requiring large
scale excavation are also subject to approval from Land Authority and other Government
bodies concerned.
2.4.2
Minimum separation between power cables and telephone cables is 0.3 m wherever
practicable. Details can be obtained from the DG, OFTA.
3.1
General
3.1.1
The Government's policy is to ensure, as far as possible, the provision of a piped gas
supply to domestic consumers, particularly to new building developments, as a means of
discouraging the future growth of liquefied petroleum gas cylinders. In this regard, a
piped gas supply in the form of town/natural gas or from a bulk liquefied petroleum gas
(LPG) storage installation should be planned for all new developments.
3.1.2
The Gas Safety Ordinance (Cap. 51) and its subsidiary regulations which became effective
on the 1st April 1991 must be complied with when a gas supply is considered.
3.2 Piped
Gas Supply
3.2.1
A piped gas supply can be made available by:
(a) the provision of town/natural gas through the conventional
reticulated supply system of the Hong Kong and China Gas Co. Ltd.;
(b)
the supply of LPG from a centralized LPG storage facility
located within the development area to be served. The size of the development area can
range from a large housing estate such as Mei Foo Sun Chuen to a single house; and
(c)
a form of substitute town/natural gas supplied by the Hong
Kong & China Gas Co. Ltd. through a reticulated supply system from temporary LPG/air
mix plants. When town/natural gas becomes available, the LPG/air mix plant would cease
operation. The town/natural gas would then be supplied to consumers through the
reticulated supply system in existence.
3.2.2
The advice of either the Hong Kong & China Gas Co. Ltd. (for town/natural gas) or the
potential LPG supplier (for LPG) should be sought at the earliest possible stage in the
design of the development or redevelopment proposals.
3.3
Guidelines on Provision
Town/Natural Gas
3.3.1
The production, storage and distribution of town/natural gas require the building of gas
works, gas holder stations, pressure reduction equipment and a pigging system ranging from
high to low supply pressures. Gas works and gas holder stations are very specialized
facilities and need to be dealt with on an individual basis, taking account of hazard
assessments. Gas pressure reduction station installations are required for reducing the
pressure from a higher pressure pipeline system to a lower pressure system. The site area
required for installing the pressure reduction equipment is dependent on operation
requirements and can vary from 12m2 to 2000m2. Generally, the supply
pipes should be laid underground, however, due to various technical reasons, alternative
installation methods may be considered. As for the location and safety separation distance
requirement for pipelines, the EMSD (Gas
Standards Office) is the authority to advise. No supply pipes should be accommodated in a
highway structure which is a sole access or carries a strategic route. However,
consideration should be given to waive the constraint when there is no alternative route.
Close liaison between Highways Department and the gas company at the early planning stage
will be necessary in identifying an acceptable routing arrangement.
Centralized LPG supply
Installations
3.3.2
A permanent site located within the development areas being served is required. However,
the size of the storage area required, the safety distances needed, and the laying of
pipes would be subject to advice of the EMSD (Gas
Standards Office). As a general rule, the installations should be secure, sited in a well
ventilated area and accessible by vehicles for replenishment and emergency service.
Substitute Town/Natural Gas
3.3.3
A temporary LPG/Air mix plant could be located in the vicinity of the township or
development being served but not necessarily immediately adjacent to it as substitute
town/natural gas can be supplied over long distances by underground pipelines. However,
the plant should be located in a well ventilated area where other utility services, such
as water and electricity are available and accessible by vehicles for replenishment and
emergency service. Whilst the gas production installation itself is temporary, the
reticulated supply system is permanent and could be connected with the town/natural gas
supply subsequently. The location and site area of a LPG/air mix installation will depend
on the number of consumers to be served. The number of consumers determines the quantity
of LPG to be stored, vaporization and air-mix plant requirements; these in turn determine
the safety distances needed between the installation and adjacent buildings and fixed
points of ignition. The advice from the EMSD (Gas
Standards Office) should be sought.
Hazard Assessments
3.3.4
Hazard assessments for gas works, gas holder stations and LPG installations form an
integral part of the project evaluation and additional safety measures may need to be
incorporated into the design of the installations to ensure that the risk posed to the
general public is minimized. Reference should be made to the risk guidelines in
Chapter
12
and procedures laid down by the Coordinating Committee on Land Use Planning and Control
related to Potentially Hazardous Installations should be followed. The EMSD (Gas Standards Office) is the authority for such
hazard assessments. The Land Authority shall notify the gas company concerned of any
development (permanent or temporary) that is proposed within a distance of 3m either side
of a high pressure (up to 35 bar) gas pipelines.
4.1
General
4.1.1
Local fixed telephone service is one of the local fixed telecommunications network services (FTNS). The local FTNS licensees are PCCW-HKT Telephone Limited (PCCW-HKT), Hutchison Global Crossing Limited (HGC), New T&T Hong Kong Limited (New T&T) and New World Telephone Limited (NWT).
4.1.2
International telephone service is one of the external telecommunications services
(ETS). The FTNS licences of PCCW-HKT, HGC, New T&T and NWT have been amended to provide non-exclusive
ETS. In mid- 2001, about 200 companies were awarded the Public Non-exclusive Telecommunications Services Licence to provide
ETS.
4.2
Telephone Network
4.2.1
A telephone network comprises subscriber premise apparatus, subscriber lines, telephone
exchanges and junction circuits.
4.2.2
Each subscriber premise apparatus is connected by a pair of subscriber lines to a local
telephone exchange where switching and connection are conducted between two subscribers.
4.2.3
From the input telephone number, the switching equipment in the telephone exchange will
locate the called party who may be in the same exchange or in another exchange.
4.2.4
The communication links provided between exchanges are junction circuits which are to
carry inter-exchange calls. The junction circuits consist of Telephone Cables Systems and
Radio Telecommunication Systems.
4.3
Telephone Exchanges
4.3.1
Generally, all telephone exchanges accommodate local exchange equipment. In some telephone
exchanges, there may be other types of exchange equipment serving different functions of
tandem, toll or other services. Local and tandem exchanges are more common.
(a)
Local Exchange
Local exchange is where subscriber
lines are terminated. Each local exchange serves its nearby communities. Depending on
geographical situations, the density of population and business, the number of subscriber
lines served by a local exchange may vary from a few hundreds to 120,000. There are about 90 local exchanges in mid-2001.
(b) Tandem
Exchange
Tandem exchanges are employed to
relay telephone calls between local exchanges. They are usually co-sited with local
exchanges.
4.4 Guidelines on Provision
4.4.1
In order to meet demand for telephone service in a new town or redeveloped area on time,
the FTNS operators should be advised of the scale of development at an early
planning stage. The FTNS operators will investigate if telephone service can
be provided from an existing local exchange, by any other methods or a new exchange is
required.
Telephone Exchange
4.4.2
No direct standard can be derived for land reservation as the size of site varies with a
number of factors such as the number of lines and type of switching equipment. However,
the following can be adopted as general guidelines:
(a) For local exchanges in rural areas
with less than 10,000 lines, a site area of about 500m2 is required.
(b) For local exchanges in urban areas
with 20,000 to 60,000 lines, a site area between 1,000m2 to 1,500m2
is required.
(c) For local exchange in urban areas
with up to 120,000 lines, or combined local/tandem exchanges or telephone exchanges
complexes (operator center, office, computer room, exchange), a site area ranging from
1,500m2 to 2,000m2 is required.
4.4.3
In rural areas, small telephone exchanges with land reserved for minor expansion are
preferred to large ones so as to preserve the rural amenity.
4.4.4
In urban areas, telephone exchanges are normally installed in specially designed
multi-storey buildings. However, in exceptional cases, they can be accommodated within
other types of buildings with the specific telephone exchange requirements incorporated
into the building design.
4.4.5
Exchanges need to be located as near as possible to the centre of telephone service demand
for efficiency and economic reasons.
4.4.6
Exchanges should be provided with easy access to main roads for external cable plant
construction and equipment delivery. A corner site abutting two to three roads in
rectangular shape is preferable for better cable duct laying and equipment layout. With
respect to the access, parking and loading/unloading arrangements, Transport Department
should be consulted at an early planning stage.
4.4.7
In general, the site should be available for the construction of the telephone exchange
about 2.5 years before the completion of the first phase of major developments. This is to
ensure availability of telephone service to the users of the initial phases of
development.
4.4.8
Exchanges should be sited at least 200m from any power generating station, bulk in feed
substation or primary substation (i.e. at 132kV or higher voltage) to avoid the risk of
rise-of-earth potential and electrical interference which can be very critical to the
safety of the operation personnel and to the sophisticated electronic telecommunication
installations in the exchanges.
4.4.9
Telephone exchanges should be sited away from an electrified rail system, large box
culvert, mullah and cable tunnel so as to avoid blockage to the multiway telephone cable
lead-in ducts. The separation distance should be assessed on individual basis. FTNS operators
should be consulted at an early planning stage.
4.4.10
Telephone exchanges should be located away from any dangerous goods installation such as
petrol filling station and inflammable material store to avoid the risk of fire or
explosion. Moreover, they should not be located near rivers or lakes to avoid flooding
problems.
Telephone Cables
4.4.11
Telephone cables should normally be laid in underground ducts except where prohibited by other
factors such as crossing bridges, rivers and nullahs; temporary cable provision for
construction sites; provision of small quantity of overhead cable in rural area due to
economical reason and provision of overhead cable over privately-owned land.
4.4.12
Telephone cables should be placed as far as possible away from power generating or
transformer stations except those feeding the stations. Such telephone cables may require
special protection.
4.4.13
Telephone cables should be separated as far as possible from power cables. The normal
separation should be at least 0.3m. For details, the "Code of Practice - Protection
of Communication Network From Electrical power Distribution" issued by DG, OFTA
should be referred to.
4.4.14
Telephone cables should be laid as far as possible away from electrified rail systems. In
Light Rail Transit System, a minimum separating distance of 2.5 m from the nearest rail is
required. For Kowloon Canton Railway System, a minimum distance of 300 m is required.
4.4.15
In principle, highway utilities reserves should be used to carry telephone cable ducts. Consultation
with FTNS operators is required in an early planning stage of the highway.
Radio Telecommunication
Systems
4.4.16
Microwave Radio Communication Systems may be used to connect urban areas to the non-urban
areas where the use of telephone cables is impracticable or not economical.
4.4.17
They are normally installed on roof top of telephone exchange buildings. However, in
exceptional cases, they can also be installed in mobile containers located in the vicinity
of the telephone exchange, or installed by other methods.
4.4.18
In principle, the aerial equipment needs to be situated in a location which can maintain a
clear line-of-sight with the counterpart aerial equipment located at another telephone
exchange building or a hill-top radio station.
5.1
General
5.1.1
The wide range of facilities within this category makes it impracticable to set out
standardized land requirements. They should be considered on an individual basis. As a
general principle, virgin hill top sites should be avoided as far as possible, and sharing
use of existing hill top sites would be encouraged.
5.2
Guidelines on provision
5.2.1
The location and design of telecommunications structures (e.g. buildings and towers) should be determined with reference to the
"Procedure for Applications to Use or Develop Hill-top and Rural Sites for Radio-telecommunications Systems (Revised Edition, June
1997)" which is issued by the Telecommunications Authority. It is available from the DG,
OFTA.
6.1
General
6.1.1
Approximately two-third of the fresh water consumed in Hong Kong is obtained from Mainland
China via the agreement made with the Chinese Authority. The remaining one-third are
collected from gazetted water gathering grounds which occupy about one-third of the total
area of the territory.
6.1.2
The principal land requirements for fresh water supply are those for storage reservoirs
and water gathering grounds, water conduits, treatment works, pumping stations, service
reservoirs, depots, workshops and offices. Land is also required for conduits, pumping
stations, and service reservoirs for the supply of salt water for flushing.
6.1.3
Land in water gathering grounds needs not be used exclusively for water supply and there
are agreed policies by which other compatible uses may be permitted. Planning of
development or projects to be located inside or near the water gathering grounds should
follow guidelines laid down by Water Supplies Department (WSD). These are set out in the
"Working Party Report on Land Use and Development in Catchment Areas". Amongst
such other uses are notably Country Parks, Special Areas or SSSIs, and other recreational areas, etc.
6.1.4
Roofs of service reservoirs in most cases provide large level surfaces. Where they are
easily accessible from nearby populated areas and are not required by the WSD for operational reasons, they can be planned for open spaces, recreation
grounds and other compatible uses subject to proper management and appropriate safeguards.
The intention to this dual use should be agreed with the WSD before
designing a service reservoir.
6.2
Locational Guidelines
6.2.1
Service Reservoirs
(a) Service reservoirs (both fresh water
and salt water) should be located as near as possible to the area they served and,
wherever possible, sited at a level where water can be fed by gravity to the Supply Zone.
The location should avoid, as far as possible, country parks, special areas and other
environmentally sensitive areas.
(b) Where possible, difficult sites
should be avoided so as to minimize the construction costs. The design of the reservoirs
should reduce adverse visual, landscape and ecological impacts. Landscape treatments
should be incorporated in the design.
(c) Where alternative sites are
available, all of which satisfy waterworks requirements (construction costs, operation
costs, etc.), it is desirable to choose sites which are more accessible so that the roofs
can be used for recreation.
6.2.2 Pumping Stations
(a) They should normally be located
within reasonable proximity to the source of supply to ensure a positive suction head is
available.
(b) Sites for pumping stations should
have adequate vehicular access to facilitate maintenance and transportation of materials
and dangerous goods (disinfectant substances, etc.).
(c) Pumping stations should be located
away from residential or other sensitive uses, wherever possible, to minimize noise
problems. If this is not feasible, suitable control measures will need to be included in
the design of the stations (see also Section 4.2.13 of Chapter
9). If necessary,
landscaping should also be incorporated to blend in with the surrounding environment.
(d) Salt water pumping stations should be
located as near as possible to seafront with access to a source of clean sea water. It is
necessary that marine activities and drainage outfalls are kept away from the sea water
intake of the stations. A minimum clear distance of 100 m (i.e. 200 m being the total
distance of the two sides from the intake point) is normally required.
6.2.3 Treatment Works
(a) Siting of treatment works should
follow the procedures laid down by the Coordinating Committee on Land Use Planning and
Control related to Potentially Hazardous Installations.
(b) Locations of treatment works should
take account of the possible environmental impacts arising from sludge discharge, noise
from pumping facilities (see para. 6.2.2 (c) above), and physical appearance. Any sludge
discharge must comply with the established guidelines for effluent control while suitable
landscaping should also be incorporated, where necessary, to blend in with the surrounding
environment.
6.2.4 Water Mains
(a) Water mains are normally placed
underground and routed along carriageways. Where circumstances permit, they should best be
routed beneath separate reserves, like pedestrian ways, cycle tracks or amenity strips.
(b) Adequate separation of water mains
from power cables and other services should be allowed, wherever practicable.
(c) It is bad engineering practice to
route water mains close to the crest of a slope. All possible steps must be taken to
prevent leakage affecting the stability of the slope. As a general rule, all water mains
should not be placed in a slope nearer to the crest of the slope than a distance equal to
its vertical height. This is a minimum standard, but each case should be considered on its
own merits. In cases where the proposed development cannot be modified to permit the
siting of water mains outside this crest area, the slope should be designed to the
appropriate factors of safety, taking into account the effects of possible water leakage.
As an alternative, water mains can be housed within a sealed trench, ducting system or
sleeve drained to a suitable discharge point at a surface drain or natural stream. The
ducting system should be designed with a drainage capacity equivalent to a pre-determined
leakage rate. It is recommended that discharge from the ducting system be monitored at six
monthly intervals.
7.1
General
7.1.1
Drainage services include the provision, operation and maintenance of foul sewerage,
sewage treatment and disposal, and stormwater drainage infrastructures. Public drainage
services are currently provided by the Drainage Services Department.
7.1.2
The provision of such services, whether for public or private use, shall conform with the
standards and guidelines for environmental planning as set out in Chapter 9.
7.2
Foul Sewerage System
7.2.1
Sewage should be collected and conveyed in enclosed conduits which should normally be
placed underground.
7.2.2
Sewers could be located under the carriageways, footpaths, cycle tracks or amenity strips.
If this is not feasible, separate drainage reserves should be provided. The location and
alignment of a sewer should be chosen such that, during the subsequent maintenance of the
sewer, disruption to vehicular and pedestrian traffic is minimized. Where sewers are
placed under carriageways, they should be located within one traffic lane as far as
possible to minimize disruption to traffic during maintenance. Gravity sewerage systems
should be used as far as possible.
7.3
Stormwater Drainage System
7.3.1
Stormwater may be collected and conveyed either in enclosed drains or open channels.
Section 7.2.2 is also applicable to the planning and design of enclosed stormwater drains.
7.3.2
When choosing the alignment of drainage channels, account should be taken to minimize
disruption to adjacent communities and minimize land resumption. Supporting facilities
such as vehicular access should be provided to enable proper operation and maintenance of
the drainage channels. Landscaping should be considered and incorporated to blend in with
the environment.
7.3.3
Supporting drainage facilities such as channel embankments may be permitted to be used as
amenities or recreational areas and access roads as waterfront promenades.
7.4
Pumping Stations and Sewage Treatment Works
7.4.1
Sewage treatment works and stormwater and sewage pumping stations should be designed to
minimize noise, odour and visual problems. They should be located away from residential or
other sensitive areas by providing suitable buffer zones, where possible. If this is not
feasible, suitable abatement measures such as acoustic insulation, odour enclosures and
landscaping should be included in the design of the facilities.
7.5 Polder Drainage and Floodwater
Pumping Schemes
7.5.1
Polder drainage and floodwater pumping schemes are to render flood protection to villages
in low-lying areas. The scheme entails the construction of floodwater pumping station,
floodwater storage pond, and flood protective bund or wall around the villages and
floodwater storage pond.
7.5.2
Floodwater storage ponds should be located at the lowest areas of the schemes. They should
either be covered or properly fenced off for safety reasons. Under no circumstances should
public access routes be allowed through the areas of the floodwater storage ponds.
7.6 Drainage Reserves
7.6.1
Unrestricted vehicular access to Drainage Reserves should be provided at all times.
Structures of any kind should generally not be permitted unless in exceptional
circumstances.
8.1
In general, utilities will not be permitted within the boundaries of an expressway, unless
they are essential to its operation e.g. street lighting and emergency telephones etc..
Other utilities may be permitted in exceptional circumstances with the agreement of the
Director of Highways. In the planning of new development areas, provision should be made
for dedicated utility reserves on the road side pavements, such as amenity strips,
pedestrian walkways and cycle tracks etc. for the laying of various utilities such as
electricity and telephone cables, gas and water pipes etc. Whenever practicable, dedicated
utility reserves should preferably be outside road reserves. Such arrangement would help
reducing possible disruption to vehicular traffic during maintenance periods.
8.2
Adequate separation between different kinds of utility provisions shall be allowed for in
the dedicated reserves. The actual width of the reserves will vary depending on individual
circumstances and the types of utilities to be accommodated. Early consultation with the
relevant utility companies and concerned departments at the planning stage will be
necessary.

|